Traffic Advisories

We want to keep you informed about roadwork, closures and other traffic delays that can affect travel within Saanich.

Road construction and closures listed below relate to larger current projects. Additional minor roadwork may occur without representation on this page.

 Some roads in Saanich are maintained by the provincial government. Please see Additional Resources below for roadwork taking place within Saanich that is managed by external organizations.

Current Advisories:

_____________________________________________________________________

General Maintenance to Traffic Median

Area: Burnside Road at Albina Street

Impacts: Single Lane Traffic

  • All vehicles will have access.
  • There will be signs on site to assist with traffic. Please obey all traffic signs.

Expected Schedule: Wednesday, August 13, 2025;

9 a.m. to 3 p.m.

TOP__________________________________________________________________

Water Main Upgrade

Area: Cedar Hill Cross Road between Lochside Drive and Cumberland Road

Impacts: Single Lane Traffic ***Extended***

  • All vehicles will have access.
  • There will be signs and traffic control on site to assist with traffic. Please obey their directions and all traffic signs.

Expected Schedule: Wednesday, July 30, to Friday, September 12, 2025;

8 a.m. to 4:30 p.m.

TOP__________________________________________________________________

Paving

Area: Doncaster Drive between Derby Road and Glacier Place

Impacts: Road Closure

  • Emergency vehicles will have access.
  • Local traffic will have access.
  • There will be signs and traffic control on site to assist with traffic. Please obey their directions and all traffic signs.

Expected Schedule: Friday, August 8, to Monday, August 11, 2025;

8 a.m. to 3 p.m.

TOP__________________________________________________________________

Sidewalk Construction

Area: Grange Road between Burnside Road West and Laburnum Road

Impacts: Road Closure ***Extended***

  • Emergency vehicles will have access.
  • Local traffic will have access.
  • There will be signs and traffic control on site to assist with traffic. Please obey their directions and all traffic signs.

Expected Schedule: Monday, July 21, to Friday, August 15, 2025;

7:30 a.m. to 4 p.m.

TOP__________________________________________________________________

Sidewalk and Crosswalk Construction

Area: Mann Avenue at Eastridge Crescent

Impacts: Single Lane Traffic ***Extended***

  • All vehicles will have access.
  • There will be signs and traffic control on site to assist with traffic. Please obey their directions and all traffic signs.

Expected Schedule: Monday, July 21, to Friday, August 15, 2025;

7 a.m. to 4 p.m.

TOP__________________________________________________________________

General Maintenance to Traffic Median

Area: Shelbourne Street between McKenzie Avenue and Blair Street

Impacts: Single Lane Alternating Traffic

  • All vehicles will have access.
  • There will be signs and traffic control on site to assist with traffic. Please obey their directions and all traffic signs.

Expected Schedule: Tuesday, August 12, 2025;
9 a.m. to 3 p.m.

TOP_________________________________________________________________

Capital Construction Project: Sinclair Road Upgrades

Area: Sinclair Road

Road closure: 24/7 until further notice

Expected Schedule: through March 2026

TOP_________________________________________________________________

Watermain Installation

Area: Tyndall Avenue between Hillcrest Avenue and Serenity Place

Impacts: Single Lane Alternating Traffic ***Extended***

  • All vehicles will have access.
  • There will be signs and traffic control on site to assist with traffic. Please obey their directions and all traffic signs.

Expected Schedule: Monday, May 26, to Friday, September 5, 2025;
8:30 a.m. to 4 p.m.

TOP_________________________________________________________________

Additional Resources:

The provincial government maintains some roads in Saanich. The provincial government and other organizations may facilitate construction on Saanich roads for their projects.

What's happening in neighbouring municipalities?